Traffic Diversion effected to facilitate test run of 110KV underground cable system at Ukkadam

First trial run of the underground cable system is being taken up today between 8 am to 10 am today and the power shutdowns would be affected in Ukkadam and Karumbukadai areas when testing is carried out in the underground cable systems.


Coimbatore: Traffic diversions have been effected in the city due to a trial run being carried out in the110 kV underground cable system laid at Ukkadam. As per the arrangement the vehicles proceeding from Ukkadam to Pollachi road, and Palakad road have been asked to use Perur bypass road, Puttuvikkia, and Chunnambukalavai stretch

In the meanwhile, the first trial run of the underground cable system is being taken up today due to which power shut down have been effected in the area. The trial run is scheduled to take place between 8 am to 10 am today and the power shutdowns would be affected in Ukkadam and Karumbukadai areas when testing is carried out in the underground cable systems.



The underground cable laying works for the laying ofHT cable wires were taken up as the overhead cable wires had proved a hindrance to the implementation of the 450- the Crore flyover project near the Ukkadam Bus stand. The cable line was laid from the Ukkadam tank to the Substation stretch.

According to Highway officials,the works for theKarumbukadai- Aathupalaum second stretch of the bridge have already been expedited. The works for the 1.9 km bridge commenced in April 2018 for the first stage of the bridge span between Ukkadam to Karumbukadi at a total outlay of Rs.216 crores. The span is designed with 55 pillars and works to construct a roundtana at the bridge have also been underway near the Ukkadam bus stand.



The second stage of the bridge between Karumbukadi and Athaupalam is being implemented at a total outlay of Rs.265.44 crores. With this, the total lenght of the bridge would have a span of 2.4km.

According to Highways officials, the Ukkadam- Aathupalam bridge works is being expedited and completed in the next 10 months and opened for public utility.

Sulur Minor Girl Murder: Aunt Alleges Body Was Cremated Without Mother’s Consent

Fresh controversy has emerged in the Sulur minor girl sexual assault and murder case after a relative alleged that the g...

Coimbatore Girl Murder Case: Eeranenjam Shelter Home Elders Hold Candlelight Vigil Seeking Justice

Elderly residents of Eeranenjam shelter home in Coimbatore held a tearful candlelight vigil demanding justice for the 10...

Solayar Dam Water Level Stands at 21.39 Feet with Steady Inflow

Solayar Dam in Valparai recorded a water level of 21.39 feet as of May 24, with an inflow of 113 cubic feet per second d...

Parambikulam Dam Water Level Rises to 27.05 Feet Following Southwest Monsoon Rainfall

Parambikulam Dam near Pollachi has recorded a water level of 27.05 feet as of August 24, with continuous inflow of 45 cu...

Azhiyar Dam Water Level Stands at 64.7 Feet with Steady Inflow Following Rainfall

Azhiyar Dam near Anaimalai records water level at 64.7 feet against 120 feet capacity. Inflow stands at 320 cusecs while...

Chief Minister's Talent Search Exam Winners Visit Semmozhipoonkavai in Coimbatore

As part of the summer camp for Chief Minister's Talent Search Exam winners organized by the School Education Department...