NGT pressure sees work progress in Bellandur

Tangible work to revive Bellandur lake finally began on Monday, days after the National Green Tribunal (NGT) set a one-month deadline to clean up the 700-acre lake.

Though the Bangalore Development Authority (BDA) started weeding the lake - boats with machines are pulling out tonnes of weeds that have overrun the lake - even by conservative estimates, this will take at least four months. "The weeding of the lake area will be done in phases. After clearing each patch of the lake, we will put up aerators," said P.N. Naik, engineering member, BDA. Aerators will be installed to increase dissolved oxygen levels in the water to provide an ecosystem that can sustain aquatic life.

Meanwhile, an expert team from the Engineering Staff College of India, Hyderabad, visited the lake on the invitation of the Karnataka Lake Conservation and Development Authority (KLCDA) to identify areas that can be converted into wetlands.

A Y-junction where inlets from Koramanagala and Agaram meet has been identified for setting up a 40-acre biomechanical wetland. "This inlet contributes nearly 220 MLD (million litres a day) of sewage into the lake. Tackling this will significantly improve water quality," said G. Vidyasagar, CEO, KLCDA.

Another wetland of around 12 acres is being planned at an inlet close to HAL airport. The total cost will be Rs. 2.2 crore, he said.

Even though officials said it would be impossible to meet the NGT's deadline, they hope that with tangible work happening and a clear roadmap, they could convince the NGT of their commitment.

Following complaints and reports of major dumping of mud, construction debris and garbage on the wetlands around the nearby Varthur lake, officials have sprung into action and intensified patrolling. "The dumps seem to have been added in the past fortnight. We have taken truck numbers from residents. Owners of these trucks will be traced and cases booked against them," said Sarfaraz Khan, Joint Commissioner (Solid Waste Management), Bruhat Bengaluru Mahanagara Palike.

Meanwhile, the BBMP put up three CCTV cameras on Monday, while their Prahari vigilance vehicles were deputed in the area to catch these trucks.

As The Hindu reported on Monday, mud was being dumped seemingly on an industrial scale on over 6 acres in the inlet wetlands of Varthur lake, resulting the blockage of a primary drain as well as violation of the buffer zone norms around the 400-acre lake.
 

Four Road Accidents Reported Across Coimbatore City; Five Injured

Five people, including women, sustained injuries in four separate road accidents reported across Coimbatore city. Traffi...

TECA Welcomes Tamil Nadu Government’s Transparency Measures and No Power Tariff Hike Decision

The Tamil Nadu Electricity Consumers’ Association (TECA) has welcomed the State government’s White Paper on the TNEB and...

DVAC Searches Highways Engineer’s Residence in Coimbatore in Road Works Corruption Case

The Directorate of Vigilance and Anti-Corruption (DVAC) on Thursday searched the residence of a Highways Department engi...

No Power Tariff Hike This Year: SIMA Thanks Tamil Nadu Government

The Southern India Mills’ Association (SIMA) has welcomed the Tamil Nadu government’s announcement that there will be no...

Coimbatore Corporation Conducts Intensive Mosquito Control Drive in PN Pudur Ward

Coimbatore Corporation's 41st Ward in PN Pudur witnessed comprehensive mosquito control operations including fumigation,...

Unidentified Woman's Body Found Near Madukkarai, Police Appeal for Public Help

Madukkarai police have shared identifying details of the woman, including tattoos on her hands and the slippers recovere...