BBMP scrambling to get drains ready before monsoon

After the controversy around demolishing structures built on encroached storm water drains (SWDs), the BBMP has a lot of catching up to do when it comes to reconstructing the drain network.

Although monsoon is just a month away, the Bruhat Bengaluru Mahanagara Palike (BBMP) seems to be under-prepared to handle rains. After several areas were inundated the last monsoon due to choked drains, the BBMP had demolished several structures and recovered nearly 22 km of SWDs.

However, the civic agency has just completed concretising just 1.8 km of the drain network.

Worse, BBMP has not maintained records of the extent of drains recovered in the first phase of encroachment removal from January to July 2016.

The BBMP had identified 1,953 encroachments of which 1,225 were removed in three phases starting January 2016. A 22-km stretch, spreading across 11 acres and 21 guntas, was recovered in the second and third phase of the drive, said BBMP officials.

"A 1.8 km stretch of RCC drain in Bommanahalli has been reconstructed," said BBMP chief engineer (SWD) Siddegowda. "Work is in progress in Dasarahalli, Kasavanahalli, Byatarayanapura and Yelahanka, and is expected to be completed in three-and-a-half months," he added.

He said work was held up due to a delay in sanctioning of funds. "Now that funds have been sanctioned and work orders given, we are hoping to finish the cementing of drains by the end of the year," he added.

However, the date of completion of the project is April 2018. “Work on vulnerable parts of the drain network will be completed in two months,” Mr. Siddegowda said.

In Kodichikkanahalli, which faced the brunt of flooding last year, the drain has been left open near the opening to the lake. As a result, waste is being dumped into the drain, which ends up in the lake. "The place has become a littering spot, and there is a lot of stench and mosquitoes," said Meena Balu, a resident.

Another complaint is the slow pace of work. “Work on a SWD next to a mall in Malleswaram has been going on for several months now. Every once in a while, work is re-started and the drain is left open only to be closed a few days later,” said a resident of Malleswaram.

No proper record of drains

From January to July 2016, around 800 encroachments were removed from SWDs, but the BBMP does not have records on the extent of drains recovered.

"It was only after the flooding in July that proper records were maintained on the extent of encroached drains recovered," admitted Siddegowda, Chief Engineer (SWD), BBMP.

Re-building SWD network

Encroachments: 1,953

Encroachments cleared since January 2016: 1,225

Extent of SWD network recovered: 22 km

RCC construction completed: 1.8 km

Senior IPS officer Mahesh Kumar Aggarwal appointed Head of the Tamil Nadu Police

The Tamil Nadu government has appointed IPS officer Mahesh Kumar Aggarwal as Director General of Police and Head of Poli...

Senior IPS Officer Mahesh Kumar Aggarwal Takes Charge as Tamil Nadu DGP

Senior IPS officer Mahesh Kumar Aggarwal has been appointed as the Director General of Police (DGP) and Head of Police F...

Councillor Inspects Various Cleaning Works In Peelamedu, Coimbatore

Ward Councillor Ambika Dhanabal led comprehensive cleanliness operations across Peelameedu areas in Ward 27, Singanalur...

Coimbatore Corporation Commissioner Inspects Water Supply Operations at Koundampalayam Overhead Tank

Coimbatore Corporation Commissioner M Sivaguru Prabhakaran conducted a direct inspection of drinking water supply operat...

Two Tirunelveli Youths Arrested for Attempted ₹1 Crore Gold Jewellery Robbery Near Coimbatore Railway Station

Two men from Tirunelveli were arrested by Coimbatore city police for attempting to rob a jewellery employee carrying gol...

Coimbatore Minor Girl Murder Accused Shifted to Prison After Medical Treatment

Karthi, one of the accused in the sexual assault and murder of a 10-year-old girl in Sulur, Coimbatore, has been transfe...